Repository CI Validation

In order to provide a way for CI to ensure that the current state of a repository is valid and all necessary commits that produce generated changes have been run by developers, make validate runs a series of checks on a clean Git repository.

Specifically, the workflow used by make validate does the following:

  1. Ensure Git is clean; if not, fail.
  2. Run make charts; if Git is no longer clean, fail and leave behind the assets.
  3. Only if validate.url and validate.branch are provided in the configuration.yaml, pull in the specified Git repository, standardize the repository, and check each asset:
    • For any assets that exist in upstream, check if it is modified or does not exist in local. If so, copy it over, unzip it, and fail.
    • For any assets that exist in local but not in upstream, check if it corresponds to an entry in the release.yaml; if not, fail.
  4. Run make unzip; if Git is no longer clean, fail.

What is the release yaml file

The release.yaml is only specified if validate.url and validate.branch are provided in the repository's configuration.yaml. It is created automatically if you run make validate, which will produce a list of assets that have been modified based on your upstream repository.

When a GitHub repository is provided for this repository to validate against, the scripts ensure that any changes introduced to the current repository make no additions, modifications, or deletions to the upstream repository's charts/, assets/, or index.yaml.

However, if this were the case always, we would not be able to add charts or make modifications to existing charts!

Therefore, to signal to the scripts that you are adding a new chart to upstream, making a modification to an existing chart, or removing a chart, you will need to specify the versions under ${CHART}.

For example:

<chart>:
- <version>
- <version>
- <version>
- ...
rancher-monitoring:
- 100.0.0+up16.6.0
rancher-monitoring-crd:
- 100.0.0+up16.6.0
fleet:
- 100.0.0+up0.3.6
fleet-agent:
- 100.0.0+up0.3.6
fleet-crd:
- 100.0.0+up0.3.6
longhorn:
- 100.0.0+up1.1.2
- 100.0.0+up1.2.0
longhorn-crd:
- 100.0.0+up1.1.2
- 100.0.0+up1.2.0

Modifying Chart Versions That Exist In Upstream

One of the caveats with using the release.yaml is that renames are not supported (e.g. you cannot remove and replace a chart in a single step).

As a result, if you attempt to modify a version of a chart that already exists in upstream, both the old version and the new version must exist in the release.yaml for CI to pass. Once the changes have been merged, you can later remove the old version from the release.yaml (usually as part of a release process).

To give a concrete example of such a scenario, let's say that you have currently committed my-chart version 0.1.2-rc3. You then take the following steps:

  1. You modify the package.yaml to point at a new upstream URL that points to 0.1.2-rc4 and resolve any conflicts with the patch files under packages/my-chart-package/generated-changes
  2. You run CHART=my-chart VERSION=0.1.2-rc3 make remove to delete the older version of the chart
  3. You run make charts to produce the new assets and charts for my-chart version 0.1.2-rc4.
  4. You modify the release.yaml to replace my-chart[0] = 0.1.2-rc3 with my-chart[0] = 0.1.2-rc4.
  5. You make a PR to your repository.

In this case, CI will fail since you are attempting to remove 0.1.2-rc3 but it is not tracked in the release.yaml.

Therefore, the correct resolution would be to leave your release.yaml as:

...
my-chart:
- 0.1.2-rc3
- 0.1.2-rc4
...

That way, both the removal of 0.1.2-rc3 and the addition of 0.1.2-rc4 are accepted. Later, you can remove 0.1.2-rc3 once the PR has been committed.